Upgrading SyteLine 9 to CloudSuite Industrial 10: the report and customization checklist
Applies to: SyteLine 9.0x upgrading to CloudSuite Industrial 10 or a current release, on-premises or moving to cloud. Check Infor's upgrade guide for your exact target release
Short answer
The database conversion is Infor's tooling and your partner's job. What decides whether go-live is calm is everything custom: reports, forms, IDO extensions, stored procedures, background tasks, integrations and the spreadsheets that read the database. Inventory all of it first, retire what nobody uses, run a full test upgrade on a copy of production, then compare every surviving custom object's output against the old system before you set a cutover date. Most upgrade delays come from customizations found in the last two weeks.
What changes, in plain terms
The details depend on your exact starting and target releases, so read Infor's upgrade documentation for your path. The themes are consistent:
- The platform moves forward. The Mongoose framework, web client and supported SQL Server and Windows versions all move on. Plan server and SQL Server work alongside the application upgrade.
- The schema changes. Tables, columns and standard procedures change between versions. Anything custom that touches them needs re-testing.
- Reporting direction changes. Infor's Reports Overview recommends Report-type forms and DataView-based reports for new custom reports, and describes custom SSRS reports as deprecated, though still supported. Crystal has been outside the standard reporting path since 8.03.
- Customizations need re-validation. Form customizations, IDO extension classes and event handlers have to be checked, and sometimes rebuilt, against the new version.
- If you're moving to multi-tenant cloud, direct SQL disappears entirely. See Reporting in CloudSuite Industrial without direct SQL.
The checklist
1. Inventory every customization
| Object | Where to look | Record |
|---|---|---|
| Custom reports | Report forms, Background Task Definitions, the report server | Who uses it, last run, data source |
| Crystal reports | File shares, menus | Same, and flag them for conversion |
| Form customizations | Forms in Design Mode, customization records | What changed and why |
| IDO extensions and custom IDOs | The IDOs form, deployed assemblies | Methods and what calls them |
| Custom stored procedures, views, tables, triggers | SQL Server, custom name prefixes | What uses them |
| Background tasks | Background Task Definitions, EXE and SP types |
What they run, schedule |
| Event handlers | Event Handlers form, especially copies of standard handlers | Active or not |
| Integrations | EDI, web store, warehouse, BI, file exports | Tables and IDOs they touch |
| Spreadsheets and BI | Logins connecting to the database | Owner and purpose |
The Background Task Definitions guide and SQL table cheat sheet help with the technical side.
2. Retire before you migrate
For each item, ask: is it used, is it still needed, does a standard feature now do it? Every report or customization retired is one less to rebuild and test. Get the business owner to sign the retire list.
3. Run a test upgrade on a copy of production
Upgrade a recent copy of production in an isolated environment, following Infor's procedure for your path. Log every failure. Custom tables, procedures and triggers that clash with the new schema usually show up here. Plan for at least two test upgrades: one to learn, one to time.
4. Fix and convert in the test environment
- Rebuild or adjust custom reports. Decide per report whether it becomes a Report-type form, a DataView, a modified standard report or a rebuilt SSRS report. See SyteLine reporting options.
- Re-apply or rebuild form customizations and event handlers. Decide each FormSync keep-or-remove prompt from your customisation register, not on the day. See Why SyteLine form changes disappear.
- Recompile and test IDO extensions against the new framework.
- Update custom stored procedures and views for schema changes, and fix any joins missing
site_refwhile you're there. - Re-point integrations and test them end to end. Integrations that write straight to tables are the ones most likely to break. Moving them to the IDO layer is worth considering now. See Connecting external systems with the IDO REST API.
5. Compare output, not screens
For each surviving custom report and process, run old and new on the same data with the same parameters, and compare row counts, totals and a sample of individual records. Have the business owner sign off on the comparison. This is where most silent errors are caught.
6. Test the business, not just the objects
Run full process tests in the upgraded environment: order to cash, procure to pay, plan to produce, and month-end. Include printing, emailing and scheduled tasks, which are often missed until the first morning after go-live. See How to schedule a SyteLine report.
7. Plan the cutover
Time the final upgrade from your test runs, agree a freeze, and write a step-by-step cutover plan with a rollback point. See the SyteLine go-live and cutover checklist.
How long the custom part takes
It depends almost entirely on step 1. A site with 20 custom reports and a few form changes is a short project. A site with 200 reports, Crystal, several integrations and undocumented SQL jobs needs months of work on customizations, regardless of how fast the database converts. Inventory first, then plan.
FAQ
What's the hardest part of a SyteLine 9 to 10 upgrade?
Usually the customizations: custom reports, form changes, IDO extensions, stored procedures and integrations, rather than the database conversion itself.
Do custom SyteLine reports work after an upgrade?
Some do, many need changes. Re-test every custom report against the upgraded database, and compare output with the old system.
Should we convert Crystal reports during the upgrade?
Yes, if they're still used. Inventory them, retire the unused ones, and rebuild the rest as Report-type forms, DataViews or SSRS reports.
How many test upgrades should we run?
At least two: one to find problems, and one to rehearse and time the real cutover.